Pre qualification questionnaires and PAS 91
Contents |
[edit] Introduction
The term ‘standard selection questionnaire’ is rather self-explanatory - these questionnaires, therefore, are often standard sets of questions buyers pose to potential suppliers as part of the tender process.
Pre qualification questionnaires in construction are used by buyers as the first stage of selection. Typically, this is a box-ticking exercise that includes basic company information and checks statements of non-collusion.
Note that since this article was written Procurement Policy Notice (PPN) 03/24 clarified that PAS 91 is no longer actively supported (or updated) and that the Common Assessment Standard (CAS) is the preferred pre-qualification questionnaire for public projects. Version 4 of the Common Assessment Standard (CAS), was published on July 4 2024, and included a new Building Safety, ensuring it can be used to demonstrate companies have the organisational capability to fulfil their roles under the Building Safety Act.
For more information see article the common assessment standard.
[edit] The first stage of the PQQ
Pre qualification questionnaires are designed to act as the first stage of vetting to ensure that businesses:
- Are financially stable.
- Meet the buyer’s due diligence requirements.
- Possess the appropriate experience and technical capability to deliver the works.
Pre qualification questionnaires in construction can vary from buyer to buyer. They may use different names such as SQ (selection questionnaire) or SSQ (standard selection questionnaire). Pre qualification questionnaires (PQQ) are often marked using the pass/fail scoring methodology. They have clear yes/no answers or minimum scores for each section to be considered for the next stage.
Depending on whether the process follows the open or closed procedure, the PQQ and initial tender may be required to be completed at the same time. For the latter closed procedure, vendors must first pass this initial stage of vetting prior to completing the main tender exercise.
[edit] Evaluating the PQQ
This is one of the few sections on a typical PQQ where vendor responses are marked with scores, often with a minimum threshold required to pass to the next stage. The typical question, shared across lots of pre qualification questionnaires in construction is this:
"Please provide details of up to three contracts, in any combination from either the public or private sector, voluntary, charity or social enterprise (VCSE) that are relevant to this requirement. VCSEs may include samples of grant-funded work. Contracts for supplies or services should have been performed during the past three years. Works contracts may be from the past five years."
Word counts can vary from buyer to buyer - some requiring from as little as 200 words to larger, 1000+ word responses. Regardless, the case study should include key sections, detailing:
- The situation: An introduction.
- The task: The specifics of the task (for example, conducting boiler services and repairs across 1000+ plus properties).
- The actions: How was the contract delivered, including key challenges or issues.
- The results: A final summary detailing the successes of the contract.
Factual recall of events should be relevant to the scope of works for the contract and should demonstrate how this performance/experience makes the vendor a suitable provider.
[edit] The PAS 91
PAS 91s had been becoming increasingly popular in the construction industry, but is now effectively replaced by the Common Assessment Standard (CAS). This questionnaire had been developed by the British Standards Institute to save companies from filling out several different PQQ's. The main benefits of completing a PAS-91 were:
- Exemption granted from some core sections if the required accreditations are held.
- Questions for the core modules standardised, which meant companies coul develop standard responses to use every time.
Exemption from individual categories could also be granted through holding certain accreditations - such as an ISO 9001 quality management certificate for the performance management section. This is typically standard, however, there are sometimes slight variations from buyer to buyer. Those companies without accreditations have to answer questions in the optional and core modules.
[edit] Common Assessment Standard (CAS)
Version 4 of the Common Assessment Standard (CAS), was published on July 4 2024, and included a new Building Safety section, ensuring it can be used to demonstrate companies have the organisational capability to fulfil their roles under the Building Safety Act. Procurement Policy Notice (PPN) 03/24 clarified two issues, that PAS 91 is no longer actively supported (or updated) and that the Common Assessment Standard (CAS) is the preferred method for pre-qualification in public projects. For more information see article the common assessment standard.
As with PAS1 CAS also notes a number of potential exemptions, where company holds any of the following certifications:
- ISO 9001
- ISO 14001 / EMAS
- ISO 27001 / Cyber Essentials Plus
- ISO 45001 / SSIP
- BS 99001
- ISO 19650-2
[edit] Relationship with tenders
Buyers can potentially receive hundreds of tender submissions for a single contract, and as such, it’s in their interest to ensure that suppliers are both vetted and checked to ensure they both fulfil their legal obligations but also that inadequate suppliers can be excluded as early as possible, saving both time and money.
[edit] Related articles on Designing Buildings
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.